Road Construction

Client: KRG
Year: 2013
Duration: 210 days
Work Location: BARZAN – DORE

Scope of Work

The project consisted of two main items:

A-Surveying and designing work for the plan and profile of the road.

B-Execution of all project items. Project activities included:

  • Cutting Works in rock areas with Jack-Hammer Work (154,887) m³.
  • Sub-base Course and crushed stone .
  • Bituminous pavement of two layers (Stabilizer and Binder).
  • Retaining wall of (2,568) m².
  • Culverts with different dimensions.
  • Gutter- Ditch Works(850m.l).