Road Construction

Client: KRG
Year: 2010
Duration: 540 days
Work Location: Erbil – Permam – Sari Blnd ((Black Top))

Scope of Work

The project included Cutting Works in rocky areas with Jack-Hammer cut volume was about (63,269) m³.

filling activities with two layers of Sub-base and paving with two layers of asphalt as well as constructing of a gravity retaining wall in addition to concrete culverts of different dimensions and.

The total length of the road was (5.6) km.

All project activities were achieve in a very successful way.

The project included casting three concrete water tank of (120) m³each.