Installation of security facilities at BVS3

Client: Kurdistan Pipeline Company Ltd.
Year: 2022
Duration: 180 Days
Work Location:Duhok (block valve station 3)

Scope of Work:

Design, supply and installation of prefabricated
security caravans with all required Civil and MEP
works.
– Steel Support fabrication, Galvanized Steel
Platforms and steel shelters
– Supply, install, and commission of 5000 litters
Diesel storage tank made by carbon steel and
performing required NDTs.
– Supply and install Booster pump platform
(Including all the required electrical, mechanical
and civil works)
– Design, Transportation and installation of
270 Reinforced T-walls and jersey barriers and
providing survey work, surface grading and
leveling, earthworks, compaction of subgrade and
subbase layer, and concrete base.
– Sewerage system: Provision of manpower,
materials, equipment, and tools to supply and
install sewerage system