Client: Kurdistan Pipeline Company Ltd.
Year: 2022
Duration: 120 Days
Work Location: Kurdistan pipeline stations
KPS2R and RETM
This EPC Contract included the project
management, engineering, procurement, supply
Installation and repairing of (Cladding and
Insulation Damages) for all piping in the stations.
– The works included overall cladding defects,
Inspection and NDTs of conditions of all KPS2R
and RETM piping insulations.