Client: Kurdistan Pipeline Company
Year: 2022
Duration: 180Days
Work Location: KPC Stations 17 Stations
The Scope of this project includes inspection of
conditions and records, Field measurements, and
diagnose the existing civil and structural defects
and propose the perfect remedy for the defects.
HMH Company consists of a team of
experts dedicated to carrying the scope for all the
inspections including the concrete structures
According to ACI 201.1R steel structures in
accordance with AISC 360. Recording the nature
of observed problems and identifying affected
components while collecting all the data and
finally turning them into professional reports for
Each of the 17 Kurdistan Pipeline Company
Stations. (KPS1, REFY, BVS1, TATA, KIN2, KIN1,
REST, RETM, KPS2R, BVS2, BVS3, FKMS, BVS4,
KPS0, KP0, KIN0, BVS0)