Client: Gulf Keystone
Year: 2019
Duration: 90 days
Work Location: SHAIKHAN Block
Peak no. of Workforce on Project: 140 Persons
Explosives Used on This project: 25 Tons
Peak no. of Heavy Equipment on Project: 115
Site preparation and civil works associated with the construction of a drilling location. The work also includes the construction of an access road and camp locations along with the required infrastructure. supply all supervision, services, labour, materials and equipment required to complete the works. Furthermore, The Worksite will be SH-I well location in the GKPI’s Operating Area designated as Block K-5, (Shaikan) which is located in northwest Kurdistan, Iraq as shown below. A rig pad location needs to be constructed, including the construction of a new road. The road to be built, branches from the SH-5 Well Pad Access Road and rises gently max % 9 for approximately little less than six kilometers. The rig pad is to be 140m long and 130 m wide to be constructed. Overview of works required is: 1. Civil construction of access roads. 2. Civil construction of a rig site complete to deploy a drilling rig, and other civil construction infrastructure required support drilling operations 3.Civil construction of Main Camp, OPF and Security Camps and security checkpoints complete to deploy infrastructure required to support security operations.